CHEYENNE, Wyo. — The Wyoming Transportation Commission awarded $41.2 million in contracts for nine Wyoming Department of Transportation construction projects during its Dec. 15 regular business meeting.

The commission conditionally awarded a nearly $17.96 million bid to Casper-based Oftedal Construction, Inc. for a project involving grading, traffic control, drainage, electrical, concrete, sidewalk and curb and gutter work on approximately half a mile at various locations within Sheridan County. The bid is conditionally awarded pending concurrence by the City of Sheridan. If approved, the contracted completion date is Nov. 30, 2024.

The commission awarded a $7.47 million bid to Cheyenne-based Reiman Corp. for a project involving paving, structure replacement, grading, milling, traffic control and other work on about 8 miles of Wyoming Highway 223 in Laramie County.

Advertisement

S & S Builders, LLC, based out of Gillette, was awarded a $2.72 million bid for a project involving bridge rehabilitation, paving, concrete work, traffic control and other work in various locations within Fremont and Park Counties.

The above two projects contracted completion dates of Nov. 30, 2023.

Lovell-based Mountain Construction Company was awarded a $7.12 million bid for a project involving paving, grading, traffic control and other work on almost 9 miles of U.S. Highway 14A in Big Horn County.

Advertisement

The commission awarded a $5.52 million bid to Afton-based Avail Valley Construction-WY, LLC, for a project involving paving, traffic control, structure rehabilitation, milling, chip seal and other work on about 5 miles of U.S. Highway 26/U.S. Highway 287 in Teton County.

Worland-based McGarvin-Moberly Construction Co. was awarded a $2.04 million bid for a project involving paving, erosion control, traffic control, chip seal and other work on approximately 5 miles of Wyoming Highway 431 on Gooseberry Creek Road in Washakie County.

The above three projects have contracted completion dates of June 30, 2024.

Advertisement

Cheyenne-based Knife River was awarded a $2.27 million bid for a project involving paving, traffic control, grading, milling, chip seal and other work on about two miles of U.S. Highway 26/Wyoming Highway 789 in Fremont County.

S & S Builders was also awarded an almost $1.37 million bid for a project involving work on the Catchnet structure system, grading, traffic control and other work on U.S. Highway 16 in Johnson County.

Advanced Electrical Contracting, Inc., based out of Sheridan, was awarded a $679,743 bid for a project involving electrical work, concrete paving, sidewalk work, curb and gutter, traffic control, grading, striping and other work at the interchange of Interstate 80 and Wyoming Highway 150 on Front Street in Uinta County.

Advertisement

The above three projects have contracted completion dates of Oct. 31, 2023.

All of this month’s awarded projects are primarily funded with federal dollars. Almost all WYDOT projects are awarded to the lowest bidder.